A hint to get started
Use a large sample when individual times need not be normal
A large number of students in a college have completed a geography project. The time, hours, taken by a student to complete the project is noted for a random sample of 150 students. The results are summarised by , .
Find unbiased estimates for the population mean and variance.
Test, at the 5% significance level, whether the population mean time for a student to complete the project exceeds 30 hours.
State, giving a reason, whether any assumption about the population is needed for the test to be valid.
[N2007/II/7]
CJC · Lecture · Example 3
Define the population mean, identify the unknown and choose the tail from the stated alternative. Keep unrounded values until the final answer.